Four stages, from a stand-alone roof to a grid tie. The concept is the same for the carport and the pool house; the permit drawings are not. These are concept diagrams; your one-line for the permit is your own.
The stages only build on each other if the first battery and inverter belong to one maker’s system that supports every later step. Mixing makers is where upgrades turn into tear-outs. Before Stage 1, confirm in the manufacturers’ own installation documents that the chosen equipment can:
If any answer is no or unknown, plan for that part to be replaced at the later stage and say so in the quote.
The roof and a battery run the structure’s own loads: pump, salt chlorine generator, lights, fans, fridge, outlets. No connection to the house or the utility, so no interconnection approval. Building and electrical permits still apply. Code: NEC Article 710 (stand-alone systems) along with 690 and 706. The inverter, battery, solar and any generator or controls the maker requires must form a complete, maker-supported stand-alone system. If the owner wants it generator-free, find equipment the maker supports that way, and check that it also supports the later stages.
A feeder from the battery to a transfer switch or backup panel at the house. When the grid drops, the switch isolates the house from the utility and the battery carries the chosen circuits. In a supported multimode system, the battery inverter forms the AC the microinverters need, so solar keeps refilling the battery during the outage. Test that in commissioning with the grid actually off.
A charger on the post charges the vehicle from the roof. Sending power back to the house takes a transfer arrangement approved for that vehicle: the maker’s own kit, or a third-party system the maker expressly supports, like Ford’s GenerLink option. Never a generic interlock, cord or transfer switch without documented suitability.
| Vehicle | Home backup equipment | Output |
|---|---|---|
| GM EVs (Silverado EV, Sierra EV, Hummer EV, Equinox EV and others) | GM Energy V2H Bundle: the PowerShift bidirectional charger plus the V2H Enablement Kit (Home Hub, inverter and a dark-start battery that boots the system in an outage). List price $8,998. Check GM’s list of V2H-capable models, years and trims. GM says this equipment doesn’t work with other makers’ battery systems. | Up to 9.6 kW |
| Tesla Cybertruck | Two separate setups. Without a Powerwall: Universal Wall Connector, Powershare Gateway and, where needed, a Backup Switch. With a Powerwall 3: the Powerwall and a Gen 3 or Universal Wall Connector. Never put a Powershare Gateway into a Powerwall system. The truck’s 9.6 kW bed outlets are a different thing. | Up to 11.5 kW |
| Tesla Model 3 / Model Y | Powerwall 3 and a Gen 3 or Universal Wall Connector (no Gateway option). Only cars with the hardware: U.S. orders from Oct 1, 2026 and some earlier builds; check the car shows “Powershare Support: Enabled” (software 2026.32.6 or later). Tesla’s current eligibility instructions offer no retrofit; check the individual car before you quote. Powerwall 2 and Powerwall+ support is listed as coming later. | Up to 11.5 kW |
| Ford F-150 PowerBoost and Lightning | GenerLink transfer switch at the meter (or beside it where the utility allows other switch types), a GenerLok cord and Ford’s 12-inch vehicle connector to the 240-volt Pro Power Onboard outlet. Fits 2021–2026 PowerBoost (7.2 kW) and 2022–2025 Lightning (9.6 kW). About $1,100 for the bundle; installation about $250–$450 at the meter or $1,000–$1,500 beside it. How the GenerLink hookup works. The utility must approve it and decides who installs. The PowerBoost runs its gas engine to keep up: outdoors only, never in a garage or under an enclosed roof. | 7.2 kW for either truck through this hookup: one 240-volt, 30-amp outlet. The Lightning’s 9.6 kW is the total across all its outlets. |
These are separate systems, not plug-in Stage 3 modules. Each may bring its own transfer equipment and energy management, and its fit with the Stage 1 battery and solar has to be documented for the exact combination. Status as each maker has announced it. Full vehicle list.
With the utility’s approval, the system interconnects to the house and starts lowering the bill. In an outage the battery inverter disconnects from the grid and keeps the backup loads running. Plain grid-tied solar without that kind of battery shuts off.
Generator Envy provides the structure and the stamped structural drawings. Wire sizes, breakers, branch circuits, the point of connection and all electrical work are designed and installed by a licensed electrician under a local permit. Code notes here are pointers to check, not legal or engineering advice; your inspector has the final say.
Spec sheet for the Generator Envy two-truck timber frame carport: sizes, panels, wiring route and point of connection.
Read it →
North Carolina enforces the 2017 NEC for one- and two-family dwellings and the 2020 NEC for other buildings; the 2023 code is delayed.
Read it →
NEC 680 distances for a pool house or solar pavilion: 5-foot bonding of fixed metal, 12-foot light and fan clearance, 6- and 20-foot receptacle rules,
Read it →
Have a question we did not answer? Write to stan@generatorenvy.com. Stan grumbles, but a real person answers.