Everything we’ve dug up on wiring a solar carport or pool house in North Carolina: which code applies, where the battery can go, what the utility wants, what the roof really makes, and what the inspector checks. Sources at the bottom. Checked November 14, 2026; products and tariffs change fast.

Home / Pros / Field guide
For electricians and builders

Which code applies in North Carolina

The full code-edition page, with section numbers →

Electrical, one- and two-family dwellings2017 NEC with NC amendments (the 2017 State Electrical Code). A carport or pool house serving a house falls here.
Electrical, everything else2020 NEC with NC amendments, in force since November 1, 2021.
2023 NECAdopted by the state but on indefinite delay. Some jurisdictions, Cary among them, accept it now as an alternate when the plan set says so. Ask before you design to it.
Residential building code2018 NC Residential Code (based on the 2015 IRC). The 2024 NC Residential Code (based on the 2021 IRC) is delayed: first pushed back by Session Law 2024-57, it now takes effect 12 months after the first day of the month following the State Fire Marshal’s certification of conditions set in Session Law 2025-2, so there’s no fixed date yet. An owner can ask to use it now as an alternate method; the jurisdiction decides.

What the edition changes for these jobs: under the 2017 NEC, the energy storage disconnect is 706.7 (renumbered 706.15 in 2020), and there’s no outside emergency-shutdown requirement for dwelling batteries. That, and the outdoor emergency disconnect at the service (230.85), arrived in 2020 and don’t apply to a house job under the 2017 code. Article 625 in 2017 already requires EV equipment that can send power back to be listed and marked for it (625.48); later editions expand that rule.

Where the battery can go

The 2018 NC Residential Code has no battery section, so today the rules are NEC 706, the battery’s listing and the maker’s instructions. The delayed 2024 NC Residential Code adds Section R328. Its published rules are a good planning target, but the permit is judged under the code in force when it’s submitted:

A carport or pool house is a detached accessory structure, which is the friendliest location in the code. Protect a battery in a carport from vehicle impact and check its temperature limits; a battery in full sun on the Outer Banks or in a Charlotte August needs shade and airflow.

Utilities

Duke Energy (Charlotte, Lake Norman, most of the Piedmont)

Dominion Energy, co-ops and town utilities

Dominion serves northeastern North Carolina, including much of the Outer Banks. Electric co-ops (EnergyUnited near Lake Norman, for one) and town utilities write their own interconnection and meter rules. Get their application and meter-collar policy in hand before you price Stage 3 or 4.

What the carport roof makes, month by month

A benchmark, not a forecast for specific equipment. NREL PVWatts version 8, kilowatt-hours a day for 13 panels at 580 W (7.54 kW DC), modeled as 3.77 kW on each slope of the 5 in 12 gable (22.6° tilt); the built roof is 7 panels on one slope and 6 on the other. Premium module setting, 14% system losses, PVWatts’ default 1.2 DC-to-AC ratio and 96% inverter efficiency, no bifacial credit, NREL typical-year weather for each spot (the Outer Banks row too). Model the chosen modules and inverters before you quote production.

MonthCharlotte, ridge east–west (slopes face south and north)Charlotte, ridge north–south (slopes face east and west)
Jan15.315.9
Feb18.118.9
Mar24.324.9
Apr29.529.8
May33.233.4
Jun34.734.7
Jul33.133.2
Aug28.729.0
Sep26.126.5
Oct21.222.1
Nov16.217.1
Dec13.113.5
YearAbout 24.5 a day, 8,940 a yearAbout 25 a day, 9,100 a year
Outer Banks (Kill Devil Hills), yearAbout 25 a day, 9,150 a yearAbout 25.5 a day, 9,300 a year

Branch circuits and voltage rise

Voltage rise calculator

Two-wire formula: 2 × one-way length × resistance per foot × amps, for a single-phase two-conductor run with equal conductor lengths. Resistances are uncoated conductors at 75°C from NEC Chapter 9, Table 8. Check ampacity, temperature correction, terminal ratings and conduit fill separately.

Backup load worksheet

Four everyday loads are ticked to start. Tick what the owner wants running in an outage. Typical numbers; use the nameplate or a clamp meter on the real equipment. Hours are run time a day; the fridge and freezer hours stand in for their compressor cycling.

LoadRunning wattsStarting wattsHours a day
1501,2008
1008008
1,0003,0001.5
8002,2000.5
6001,2006
9001,2008
2002006
606024
2002005
1,2001,2000.25
5005008
5001,0000.1

Battery days assume 90% of the battery is usable and 90% makes it through the inverter. Size the inverter for the running total plus the largest single starting surge, with margin. A soft starter matched to the pump can cut its starting surge a lot; confirm the figure for that pump and motor. This is a screening tool: final inverter sizing also weighs simultaneous starts, 120-volt leg balance and the inverter’s surge duration.

Pool houses: NEC Article 680

The full pool house page →

A pool house isn’t a carport with different loads. Show the pool edge and the distances to the structure on the site plan, and work through Article 680:

Commissioning and handoff

First visit: site survey

The permit packet

From us: the stamped structural set for the site, the frame drawings showing the wire chase, the hole through the plate and the conduit stub in the footing, and the panel layout.

From you, depending on the county: the electrical permit application; a one-line for the stage being built (ours are a starting point); a site plan with the trench route, burial depth and disconnect locations; spec sheets for panels, microinverters, clamps, battery, transfer equipment and charger; a load calculation where the service or a feeder changes; and for a grid tie, the utility’s interconnection approval.

What inspectors look for

Questions we get

Geek button Is the carport a separate structure?

Yes, when it’s detached. A feeder to it follows Article 225 and 250.32: an equipment grounding conductor, a building disconnect and a grounding electrode at the carport, plus an insulated neutral when there are 120-volt loads, never bonded to ground there. A structure fed by a single branch circuit (a multiwire one counts) with an equipment ground is exempt from the electrode under the 250.32(A) exception. A ground rod is never the fault path; the equipment ground is.

Geek button Does Stage 1 need the utility?

No. Nothing connects to the house or the grid. It still needs building and electrical permits.

Geek button Can we start at Stage 1 and add later?

Yes, if the first equipment is picked for the planned additions and the maker supports them. Pull a conduit big enough for the later feeder on day one so nobody trenches twice. Later stages can still need different inverters, transfer equipment, protection or controls.

Geek button Where do the microinverters go?

On top of the ridge beam, under the panels, one per panel. The trunk cable runs along the ridge top and down the end rafter to the post with the wire chase.

Geek button Who needs which license?

Electrical work needs a North Carolina electrical contractor license. A general contractor license is required when the total project cost is $40,000 or more.

Sources

Generator Envy provides the structure and the stamped structural drawings. Wire sizes, breakers, branch circuits, the point of connection and all electrical work are designed and installed by a licensed electrician under a local permit. Code notes here are pointers to check, not legal or engineering advice; your inspector has the final say.